Difference between lump sum and measurement contracts
Lump sum and measurement are both types construction contracts.
Under a lump sum contract, a single ‘lump sum’ price is agreed before the works begin. This is a type of 'fixed price' contract, where the contractors agree to execute the works described in the contract for a total sum of money (the contract sum). Lump sum contracts are generally appropriate where the project is well defined when tenders are sought and significant changes to requirements are unlikely. This means that the contractor is able to accurately price the works they are being asked to carry out.
For more information see: Lump sum contract.
NB it should be noted that whilst lump sum contracts are often referred to as 'fixed price', there are generally mechanisms within the contract to allow the contract sum to be changed, for example if variations are made, or if there are provisions to account for inflation. For more information see: Fixed price contracts.
Measurement contracts (sometimes called ‘re-measurement’ or ‘measure and value’ contracts) are generally used in situations where the design (or type of work required) can be described in reasonable detail, but the amount required cannot. For example, excavation works where the quantity of excavation required is difficult to assess until after the works have begun. The contract sum for measurement contracts is not finalised until the project is complete. At this point it is assessed on based on re-measurement of the actual amount of work carried out.
Measurement contracts can allow an early start on site, before design is complete, and they can allow changes to be made to the works relatively easily. However, there is inevitably some risk for the client as the cost of the works is not known. In effect, the client is taking the risk for any ‘unknowns’, and whilst this can result in competitive prices from contractors, the level of uncertainty for the client means that measurement contracts are rare other than on civil engineering projects.
For more information see: Measurement contract.
[edit] Related articles on Designing Buildings
- Construction contract.
- Contract sum.
- The difference between admeasurement and construction management contracts.
- Fixed price contract.
- Lump sum contract.
- Lump sum contract - pros and cons.
- Measured term contract.
- Measurement contract.
- Procurement route.
- Remeasurement.
- Right to payment.
- Schedule of rates.
- Schedule of rates term contract.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Building Safety Act implementation in Wales
CIAT to host industry panel on 26 June.
New and updated CLC building safety guidance.
New UK National Buildings Database.
Building Safety Wiki Interviews
Chief executive of the British Woodworking Federation.
Planning condition discharge in England and Wales
A brief explanation from a building compliance expert, with further links.
Overheating guidance and tools for building designers
Guidance for dealing with element of building fabric control that have increasing importance.
Shading for housing, a design guide
From the Good Homes Alliance and British Blind and Shutter Association.
UK Standard Skills Classification (SSC)
A shared framework for describing skills needs.
Social media ban consultation comes to close
CIOB urges UK Government to consider social media’s role in careers guidance in ban debate.
The latest of eight Skills England apprenticeship units
The addition of battery manufacturing welcomed by ECA with a warning about the risks of fast-tracked apprenticeship units.
Building Control Independent Panel final report
A precis of a key report led by Dame Hackitt with full recommendations and link to the government response.


















Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.